Hold point: A mandatory verification position in the contract beyond which work cannot proceed without designated authorisation. Witness point: A nominated position, in the different stages of the Contract, where the option of attendance may be exercised by the Superintendent, after notification of the requirement.

What is witness point in inspection?

Witness Point (W): The manufacturer shall notify the client and TPI Inspector, but there is no hold on the production. The client can waive this inspection based on its discretion and inform the TPI Inspector.

What hold point means?

Hold Point means those points beyond which the stated activity must not proceed without the Superintendent’s approval to proceed. The Superintendent’s approval to proceed beyond the Hold Point does not relieve the Contractor of responsibility for satisfactory execution or performance of the work. Sample 1. Sample 2.

What is hold point in quality control?

Construction Quality Assurance/Quality Control Blog The “hold” in “hold point” refers to putting a hold on construction activities until an inspection is passed. Quality assurance departments also use this technique to reign in production when they have a habit of not completing work before moving on to the next stage.

Who prepares ITP?

ITPs are usually prepared by a quality engineer, who tests materials and surveys the processes used. Their results are then reviewed by a quality manager and construction manager, before being approved by the project manager and submitted to the head engineer.

What is surveillance Inspection?

(legal) In criminal law, an investigation process by which police gather evidence about crimes, or suspected crime, through continued observation of persons or places.

What is surveillance inspection?

What is ITP in piping?

This content provides you with a draft Pipe Inspection and Test plan. This pipe ITP is general. If you have bought a manufactured pipes so witnessing of some tests is not possible and you can only review the manufacturer test reports. …

What is inspection point in SAP QM?

An inspection point is an identifiable record of inspection results that is assigned to a work or inspection operation. Several inspection points can be assigned to an inspection operation.

Does ITP weaken immune system?

A: The specific cause of ITP is unknown, but it is known that ITP causes the body’s immune system to destroy healthy platelets that can lead to easy or excessive bruising or bleeding.

What should an ITP include?

ITPs are a plan of when, what and how you will conduct inspections to ensure your work is meeting necessary standards. It details the critical points at various stages within a process for scheduled inspections and verifications to make sure the job is progressing as it should be.

What’s the difference between observation and surveillance?

As nouns the difference between observation and surveillance is that observation is the act of observing, and the fact of being observed while surveillance is close observation of an individual or group; person or persons under suspicion.

What are the hold points and witness points?

There are two important inspection actions that must be carried out in respect of the Inspection and Test Plan, they are called Hold Points and Witness points. They are points in the construction stage where inspection or verification is required.

When does a witness point need to be released?

The work cannot proceed until the Engineer or Consultant is able to verify the quality of the completed work and releases the Hold by means of Inspection Request approval. Witness Point is an identified point in the process where the Engineer or Consultant may review, witness, inspect method, or process of work.

What is a hold point in quality assurance?

Hold Point is a mandatory verification point beyond which work cannot proceed without approval by the Engineer or Consultant or Municipality Inspector. The work cannot proceed until the Engineer or Consultant is able to verify the quality of the completed work and releases the Hold by means of Inspection Request approval.

What is the hold point in a construction project?

Hold Point: The first floor of our project is to be cast but it must be inspected by the Municipality Inspector before it will be poured with concrete. The Hold Point there is the inspection or verification of the Municipality Inspector; once the Inspection is approved it will release the Hold.